Current Construction / Road Closures


Route 9 Northbound Lane Closure Scheduled for June 8 & 9, 2020

Lane Closure Notice


Town of Malta Complete Street Project Update



April 17, 2020
Mobilization began the week of April 13 and construction work zone signage was installed.
Construction of the Blacksmith Square sidewalk portion of the project is anticipated to begin April 20th.

Town of MaltaComplete Street Project
Update June 5, 2020
Construction of the Blacksmith Square Sidewalk is 95% Complete
Work on the Gateway Signage Commenced June 1st
Saw Cutting of Pavement Along Route 9 Expected to Begin June 8th (To begin heading north from Stonebreak,
 then circle back to the west side of Route 9 heading south)Installation of Drainage Catch Basins Expected to Begin June 15th (from south to north)

Country Knolls Road Work

Sections of culvert piping and catch basins are being replaced in the Country Knolls area.
This will be done over a number of years.  The roads will be open for traffic during the work most of the time, there may be occasion for some very short closures.

LUTHER FOREST Road work


Another project that we have finally finalized planning for is the Luther Forest Catch Basins drainage.
We will be doing sections at a time each year replacing/widening drainage areas.
Kubricky Consruction will be doing the major part of the work with the Highway Department
These roads may need to be shut down for very short periods of time.

 

Thank you for your patience during this work.